Introduction to the Example Institute
A three-minute film for Example College, prepared for Jane Sample.
Filming is finished. The assembly edit has started.
Both shoot days are done and every contributor was filmed. Joe is cutting the best moments into a first story, and you will see it on this page on Friday 16 October.
Assembly edit to you by 16 October.
Nothing today. When the cut arrives, one set of combined comments is the quickest way through.
- ✓AgreementSigned 1 Oct
- ✓Script and planningAgreed 8 Oct
- ✓FilmingDone 13 Oct
- 4Assembly EditDue 16 Oct
- 5Review Round 1Of 2 · from 16 Oct
- 6Review Round 2Of 2 · to follow
- 7Final Delivery30 Oct
Edit and reviews
Joe is selecting the best moments and cutting them into a story.
- Assembly EditIn progress
- Review Round 1 (of 2)To follow
- Review Round 2 (of 2)To follow
Two review rounds are included. After that, a couple of small tweaks are fine. If you find yourself wanting many tweaks, please talk to Carl first, because that may add to the edit budget. Anything that is our own mistake we fix at no charge.
Post-production includes two rounds of unlimited amendments. If stock media is required, there may be additional cost.
Edit and reviews
Cut once the introduction film is signed off, using the same material.
- Assembly EditTo follow
- Review Round 1 (of 2)To follow
- Review Round 2 (of 2)To follow
| Deliverable | Format | Status |
|---|---|---|
| Introduction film, about 3 minutes | 16:9, subtitled | Assembly edit |
| Three social clips | Square and vertical | After sign-off |
| Short teaser for the website | 16:9, 30 seconds | After sign-off |
| Interview transcripts | Word document | Sent 14 Oct |
- 12 OctShoot day one, the laboratoryDone
- 13 OctShoot day two, the library and cafeDone
- 16 OctAssembly Edit ready to watch
- 23 OctReview Round 1 comments back from you (suggested)
- 28 OctReview Round 2 (if needed)
- 30 OctFinal Delivery
- 30 OctInvoice submitted: final balance
Dates move if a review takes longer than planned. We will say so here before anyone has to ask.
Email me when this page changes
Add your email and, as one of the team, you will be told whenever we post an update. Add colleagues the same way.
Thank you. We will email you when this page changes.
We use your email only for updates to this page. Reply to any update to be taken off.
Your agreement
Here is the Project Proposal as it was approved by you: the introduction film, the filming plan, the deliverables and the timescales.
Read the agreement